Sandy’s cabinet company uses MRP to schedule its production. due to the current recession and the need to cut costs,sandy has targeted the inventory investment area for cost reduction.

Sandy’s cabinet company uses MRP to schedule its production. due to the current recession and the need to cut costs,sandy has targeted the inventory investment area for cost reduction.

150 150 Support

Sandy’s cabinet company uses MRP to schedule its production. due to the current recession and the need to cut costs,sandy has targeted the inventory investment area for cost reduction. however, the company does not want to reduce its customer service level in the process. demand and inventory data for a standard two-drawer file cabinet are given in the following table. MRP matrix for the cabinet using (a) no lot sizing, (b) min of 200, and (c) multiples of 175 lot sizing. which lot sizing rule do you recommend?

Ordering cost = $100 per order

holding cost = $1 per cabinet per week

Lead time = 1 period

beginning inv = 150

Period: 1=145, 2=165, 3=155, 4=135, 5=170

Facebooktwittergoogle_plusredditpinterestlinkedinmail